Hongrun rotary drier machine installation requirements

Hongrun rotary drier machine installation requirements:

1, The general requirements before installation, dryer installation should be in accordance with the requirements of this specification and technical requirements of the drawings.(1) count the number of parts.(2). Remove protective coating and handling process of packaging on the coated dust and dirt.(3) repair parts surface, the gear in the process of handling damage

2, installation procedures:(1) install the wheel supporting device, and the idler wheel is mounted on the base.(2) the body gently supporting wheel device, a supporting roller retaining device.(3) installation of transmission.(4) after the adjustment of qualified grouting.(5) trial operation.(6) installation of the sealing device.

3, on the basis of the requirements:(1) according to the general basis of size and position of the anchor bolt concrete foundation.(2) the basic requirements and the inclination of slope should general body consistent. Elevation according to user's civil design.(3) according to the mechanical equipment installation engineering construction and acceptance specification for anchor bolt installation.

4, the installation of the supporting wheel and the supporting wheel device(1) between the roller device and the supporting roller retaining device base and foundation wedge wedges, to adjust the height of the base.(2) the supporting wheel, the center line of the idler wheel and the central line of the cylinder body are not coincident with the delta <2mm. as shown in Figure two (3). The surface of the supporting wheel on the diagonal of the diagonal line is pulled by two straight lines, and the crossing of the straight line should be coincident, and the degree of overlap is less than 1.5mm.

5, after the installation of the test:(1) the body will gently lift supporting wheel device, a supporting roller retaining device is required in accordance with the technical requirements of the drawings test tube installation tolerances.
(2) test method recommended in the rotation. On one side, and the radial end gear ring, both ends of the cylinder four stroke needle, rotating cylinder, measuring to at least four directions in the week, to ensure the requirements of the drawings.

6, the installation of the transmission device.(1) the slope of the transmission should be the same as that of the cylinder, with a deviation of <0.1 mm / m.(2) reducer, the motor is not more than 0.5 mm of different heart.

Hongrun series machine list:  wood crusher machinestraw crusher machine cost wood chip crusherwood powder machine crusher mill pulverizerhammer mill crushercharcoal pulverizer crusherchicken manure drying machinesgrain dryer machinerotary dryer installationtumble dryer air pipeair pipe dryer in Chinasawdust dryer for salemineral rotary dryerbox type dryer machinecharcoal rod making machinecharcoal ball making machinecharcoal tablet press machinecharcoal briquette extruder machinehoisting type carbonization furnacepalm fiber rotary carbonization furnacecoconut shell charcoal carbonization Furnacebiomass sawdust dryerBBQ charcoal equipmentenvironmental protection carbonization furnacehookah charcoal making machinecharcoal machine equipmentsmechanism charcoal machinescharcoal machines pricestraw rod making machine charcoal powder tablet press machine